Inglemoor High School

Serving more than 1,400 students, Inglemoor High School will have a phased replacement to better support student learning. This web page outlines Phase 2 of the school buildings' replacement.

 

Six red cubes labeled with steps of the school design and construction process are lined up on a white background, with a "We Are Here" marker pointing to the first step called "Project Development."

School Design & Construction Process

 

Draft site plan for the IHS Phased Replacement Project master plan as of Dec. 2023

Project Information

  • Budget: $160.5 million
  • Funded by: 2026 Capital Bond
  • Est. Completion for Phase I Construction: January 2030
  • Architect: Hutteball + Oremus
  • Contractor: Selection process in progress

Progress

  • February 2026: Voters approve the Capital Bond
  • Summer 2026: Initial design in progress of new theater / gym building, anticipate contractor selection by end of summer

Project Goals

The overarching goal of this project is to replace the existing school buildings in a phased approach resulting in an improved and modern learning environment. In 2023, we developed a master plan and design for the entire replacement project and determined the scope of the Phase 1 construction based on project priorities, construction logistics limitations, and budget constraints.

Phase 1 of the project is on schedule for completion and use in the 2027-28 school year and had the following established priorities for the replacement initiative:

  • Improve building conditions in new spaces, by building a new central plant and modernizing the HVAC system, using sustainable solutions.
  • Building a new cafeteria and kitchen for increased capacity.
  • Replace restrooms and add gender-inclusive restrooms to provide greater supervision and increase student safety in new construction spaces.
  • Construction of new classroom spaces.

 

Phase 2 of the project will focus on the following priorities:

  • Constructing a new theater and gym building in the current location of the 800/900 classroom buildings, which will be torn down.
  • Improve building conditions in new spaces by installing a modernized HVAC system, using sustainable solutions.
  • Incorporate gender-inclusive restrooms to provide greater supervision and increase student safety in new construction spaces.
  • Demolition of existing gym building and construction of new classroom space wing in its footprint, pending budget availability