Maywood Hills: August 2025 Construction Update

Maywood Hills: August 2025 Construction Update

The project's finish line is now in sight, and we couldn't be more excited! We look forward to welcoming our staff back in late August, as their presence will pave the way for students to begin the new school year in September and enjoy their new Commons building and modernized campus.

We are so grateful for your patience and support throughout this process. Thank you again for making this project a reality!

July was a highly productive month, with major milestones reached. Inside, crews finished installing all exterior and interior doors, restroom and kitchen tile, interior glass, and kitchen countertops. We also completed the final flooring on both levels, the Level 1 ceiling tile, and all casework and FRP installation. Outside, we finished installing the West retention vault and drainage structure run, and setting up the new generator. We also completed a new rock wall, covered play structure, and trash enclosure. The site is taking shape with work on asphalt paving and placing sidewalk concrete. Progress on the playground area was significant, with the installation of its asphalt, playground tiles, playground equipment, and a horseshoe-style seat bench. 

Part of new inclusive playground and existing turf field

Part of new inclusive playground and existing turf field

 

We're in the final stretch and focused on securing the Certificate of Occupancy and Health Department permit to open the new building and kitchen. Inside, teams are completing the last of the flooring, Level 2 ceiling tile, door hardware, blinds, and finish paint, classroom fan coil units, along with final adjustments to the kitchen equipment. Outside, the final steps will be installing light pole bases and the irrigation system, followed by finish asphalt, soils, and plantings. We can't wait to share these new spaces with our students, staff, and community very soon!

line drawing of the Maywood Hills campus

Maywood Hills campus layout featuring new bus loop, commons building, and play areas​​​​​​


 

For summer 2025, the entire Maywood Hills campus will be closed to the public, including field and playground. Gates will be secured, and signs posted to remind the community that the campus is under construction and not available for access.

For summer 2025, the entire Maywood Hills campus will be closed to the public, including field and playground. Gates will be secured, and signs posted to remind the community that the campus is under construction and not available for access.

On 104th Ave NE, right-of-way improvements such as sidewalk, bike lane, and paving, will be made through the summer. Traffic control crews will provide safe detours or controlled through access.

 

Aerial view of new commons building and freshly paved bus loop, parking area, and car loop.

Aerial view of new commons building and freshly paved bus loop, parking area, and car loop.

 

Inclusive playground featuring communication board

Inclusive playground featuring communication board

 

Covered play structure installed, doubles as a waiting area for students riding buses

Covered play structure installed, doubles as a waiting area for students riding buses​​​​

 

Tile installation along the Commons serving wall

Tile installation along the Commons serving wall​​​​​

 

Inclusive playground progress

Inclusive playground progress​​​​​

 

Construction crews work on the right-of-way improvements with sidewalk and protected bike lane

City of Bothell right-of-way improvements with sidewalk and protected bike lane​​​

 


 

Crews work on site improvements for the refreshed car loop, parking area, and new bus loop.

Site work at refreshed car loop, parking area, and new bus loop.​​​​​

 

First floor of commons building featuring reading nook

First floor of commons building featuring reading nook

 

 

An open, gravel area with two construction works checking the land

Most portables were demolished or salvaged. Some will remain on campus (unoccupied) until the next location is ready. ​​​​​