January Construction Update: Ruby Bridges Elementary

Ruby Bridges interior

Ruby Bridges Elementary continues to be on schedule. During January, site prep work for the accessible playground area continued and once the weather improves, concrete will be poured around the playground area. Site irrigation for the project is ongoing. 

Inside the school, ceiling grids and tiles are being placed, some parts of the building are getting final paint, the contractors are continuing to install undercounter lights and wall trims, and the elevator shaft construction is ongoing. 

All equipment in the Large On-site Sewage System (LOSS) building has been installed and commissioning will begin in June. 

This project was made possible by the generous support of Northshore voters, who approved the 2018 bond.

Continue to follow the school’s progress by visiting our construction page or by viewing the live construction camera.

Ruby Bridges accessible playground site prep

 