August Construction Update: Skyview & Canyon Creek Expansion

August Construction Update: Skyview & Canyon Creek Expansion
Skyview Canyon Creek expansion exterior

The Skyview & Canyon Creek expansion project continued to see a lot of progress during the month of August! 

Crews installed all of the new equipment in the rebuilt state-of-the-art kitchen at Skyview. Also, the addition for the two new health classrooms at Skyview was fully enclosed. 

A new space for the kiln was built at Canyon Creek. Also, a temporary wall was constructed, which will make it seamless for construction crews to continue the work on the additional gym space. 

The majority of the parking and paving work is complete at both sites and landscaping will be coming soon. 

When students return to campus, much of the focus for the construction team will return to the main two-floor addition, where they will work to finish flooring, electrical, lighting and painting. 

Continue to follow the school’s progress by visiting our construction page or by viewing the live construction camera.