Kenmore Elementary modernization project update
The design for the Kenmore Elementary modernization project has significantly matured over the last three months. All necessary permit applications have been submitted, and approval from the jurisdiction is pending to begin construction in the summer of 2024. The project team is working on finalizing the project design details and prepare for construction activity starting right after the last day of school.
Updated renderings are now available on the project website for viewing. Please note that these may change before construction begins, but they represent the most recent draft of the project design to provide an early look at what is to come.
What to expect in the next few months:
- SAVE THE DATE: A community meeting will be held on June 10 from 6-8 p.m. at the Kenmore Elementary Gym. This meeting will provide the latest design updates and discuss how construction activity will be managed on campus.
- Pre-Construction on-site work end of the school year:
- 4 double portables will be moved our starting June 26, 2024
- Contractor mobilization starting June 26, 2024
- Construction job trailer will be delivered after June 26, 2024