Crystal Springs Elementary School
Serving approximately 500 students, Crystal Springs Elementary’s growth project will address a number of needs, including site circulation and adding a fully accessible and inclusive playground, to support student learning.
Project Information
- Budget: $30.75 million
- Funded by: 2022 Capital Bond
- Est. Completion: September 2025
-
Design-Build Team: NAC Architecture and Abbott Construction
-
Parking & Transportation Information: Parent Drop-Off and Pick-Up Instructions for 2024-25
Progress
-
February 2022: Voters approve the Capital Bond
-
November 2022: Progressive design builder team of NAC and Abbott Construction selected
- January and February: Community engagement on building needs. View the recording of a virtual session.
- Winter-Spring 2023: The design team met multiple times with staff and community in School Design Advisory Committee “SDAC” meetings, as well as focused user group meetings, which included students.
- September 2023: Submitted Conditional Use Permit Documents
- Summer 2024: Start of construction
- September 30, 2024: Community Groundbreaking Ceremony
Project Goals
The overarching goal of this project is to address district growth and reduce portables, improve building conditions, and improve the health and safety of the learning environment. Many decisions about the direction of the Crystal Springs expansion project were made in 2023 with input from the school and community, establishing the following priorities:
-
Reducing the number of portables and building additional permanent classrooms.
-
Install a fully accessible and inclusive playground.
-
Replace the gym and build a new commons.
-
Make habitability updates to existing buildings.
-
Improve circulation and add parking.